Widen US 101 and add Auxiliary Lanes from Marsh Rd to Embarcadero Rd |
Description: In San Mateo and Santa Clara Counties, from Embarcadero Road to Marsh Road; Construct new Auxiliary Lanes. Postmiles in Santa Clara County are from 52.3 to 52.6.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | East Palo Alto, Menlo Park, Palo Alto |
Zip Code | 94025, 94303 |
Senate District |
08, 11 |
Assembly District | 21 |
Congressional District | 12, 14 |
Caltrans District |
04 |
County/State Route | San Mateo 101 |
Postmile Begin/End | 0 3.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 13752 | 23088 |
Lane Miles Added (Mixed) | 0 | 7.2 |
Peak Period Time Savings (minutes) | 1095164 | 1838616 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Ron Moriguchi | (510) 286-5073 | ron_moriguchi@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Ron Moriguchi | (510) 286-5073 | ron_moriguchi@dot.ca.gov | |
Right of Way Phase |
Caltrans | Ron Moriguchi | (510) 286-5073 | ron_moriguchi@dot.ca.gov | |
Construction Phase |
Caltrans | Ron Moriguchi | (510) 286-5073 | ron_moriguchi@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Juliana Gum | (510) 286-4579 | juliana_gum@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$5,200 | $2,600 | $7,800 | ||||
CMIA |
$60,000 | $-33,898 | $26,102 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,021 | $-3,385 | $5,636 | ||||
Local** |
$37,168 | $-14,699 | $22,469 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $111,389 | $-49,382 | $62,007 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$5,200 | $-1,100 | $4,100 | $4,057 | |||
Design(PS&E) |
$8,525 | $319 | $8,844 | $9,070 | |||
Right of Way |
$5,406 | $-2,211 | $3,195 | $355 | |||
Construction |
$92,258 | $-46,390 | $45,868 | $26,914 | |||
Total* | $111,389 | $-49,382 | $62,007 | $40,395 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
03/01/2007 10/01/2008 |
|
03/01/2007 10/01/2008 |
100 | 03/01/2007 10/01/2008 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2008 12/01/2010 |
|
10/01/2008 08/02/2010 |
100 | 10/01/2008 08/12/2010 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
10/01/2008 11/01/2010 |
|
10/01/2008 07/16/2010 |
95 | 10/01/2008 07/13/2010 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
04/01/2011 11/01/2013 |
|
01/03/2011 03/01/2012 |
100 | 06/01/2011 06/25/2013 |
-5 -16 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2013 11/01/2014 |
|
03/01/2012 03/01/2013 |
50 | 06/25/2013 11/30/2016 |
-16 -46 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 12/01/2009 | 12/01/2009 | 0 | 12/01/2010 | -12 | ||
Implementation Date | 12/01/2009 | 12/01/2009 | 0 | 12/01/2010 | -12 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 13752 | 23088 |
Lane Miles Added (Mixed) | 0 | 7.2 |
Peak Period Time Savings (minutes) | 1095164 | 1838616 |
Bond Funding Cost | |
---|---|
Adopted: |
$65,200,000 |
Current Approved: |
$23,445,000 |
Actual Expenditures: |
$17,990,000 |
Status as of December 31, 2023.